William Griffin, P.E., PSP, CCA
Pennsylvania

1777 Sentry Parkway West
VEVA Building 11, Suite 300
Blue Bell, PA  19422
Tel: 267-464-0500
Fax: 267-464-0400

William Griffin, P.E., PSP, CCA

William Griffin has over ten years of experience in construction and manufacturing scheduling, delay & disruption claims analysis, design, engineering, project management, commissioning, and quality control. He has evaluated over $1 billion in claims and worked on the behalf of owners, architects, engineers, and contractors on a variety of commercial and public projects including hospitals, laboratories, offices, schools, housing complexes, prisons, stadiums, railroads, roadways, bridges, airports, conveyors, wastewater treatment facilities, levees, production plants, spent nuclear fuel storage facilities, substations, and a helicopter development program. William prepares and analyzes schedules and claims through extensive review project drawings, specifications, and correspondence. He lectures on scheduling, delay, and disruption and he regularly prepares schedules, expert reports and presentations.

Education
  • University of Alabama at Birmingham, M.Eng, concentration in Construction Engineering Management
  • Drexel University, B.S., Mechanical Engineering
Licenses/Credentials
  • Professional Engineer: Pennsylvania
  • AACE International, Planning and Scheduling Professional
  • National Association of Construction Auditors, Certified Construction Auditor (CCA)
Professional Affiliations
  • Association for the Advancement of Cost Engineering International (AACE)
  • American Society of Civil Engineers (ASCE)
  • Project Management College of Scheduling (PMCOS)
  • National Association of Construction Auditors (NACA)
Select Speaking Engagements

“Analyzing Delay with Inaccurate Schedules – A Case Study,” Project Management College of Scheduling Conference, Vancouver, British Columbia, May 2018.

“Construction Scheduling and Claims,” Widener University’s Professional Practice Course, Chester, PA, April 2016; April 2015; April 2014.

Select Testimony

Crown America International, Inc. v. Clemens Construction Co., Inc., American Arbitration Association, Case No. 01-19-0001-7630. (Testimony)

Project Highlights

Coal Combustion Residue Waste Conveying System – Analyzed delays and added costs during fabrication and construction of a one-and-a-half mile long pipe conveyor that carried ash to a truck loading station. Evaluated the impacts of the late issuance of design and shop drawings, late truck loading station steel deliveries, mis-fabrication of all truck loading station steel and its return to the manufacturer for repairs, redelivery of truck loading station steel, and the subsequent on-site repairs of the redelivered steel. Compared truck loading station construction delays to delays in construction of the pipe conveyor to determine compensable and concurrent delays. Evaluated contractor’s work orders and cost report to determine added costs resulting from the mis-fabricated truck loading station steel. Prepared a CPM schedule analysis. Assisted in preparation of an expert report. Assisted in the preparation of an arbitration presentation which resulted in a full award being granted.

Children’s Hospital – Analyzed $10 million in claims by the Mechanical & Plumbing contractor on a five-story 250,000 square foot hospital. The contractor alleged added scope due to BIM coordination, loss of productivity, and various unpaid change orders. Evaluated the validity of loss of productivity and air handling unit redesign costs. Assisted in the preparation of an expert report and a mediation presentation.